1. Appointment and scope.
Bulk floor is intended for high-quality leveling concrete, cement peschannykh and other bases. Does not demand preliminary alignment by a coupler. Are used in and outside of premises of different function under the following final covering: linoleum, parquet, ceramic tile.
2. Preparation of a surface.
For preservation of optimum adhesive properties of the self-leveling floor the basis is cleared of dirt, dust, fats, by oils, paint and other water-repellent substances interfering coupling. For obtaining rating strength data of a floor, a surface of the basis process a primer surely!
3. Solution preparation.
For solution preparation to fill up dry mix in the container with clear water, water temperature has to be not below +15 °C (optimum 18-25 °C), on 25 kg of dry mix of 8-8,8 l of water depending on the estimated thickness of the put coat layer. At a thickness more than 5 mm the amount of water decreases if mix of more dense consistence is required. To allow solution to be defended 3-5 min. and then again actively to mix before obtaining the homogeneous easily mixed mass. The prepared portion of solution has to be spent within 30-40 min.
4. Performance of work. For receiving a horizontal floor to pour the prepared solution evenly on a surface of the prepared basis. Mix with more dense consistence (for laying of a layer more than 5 mm thick) if necessary can be dissolved on a surface by means of a rigid broom, a rubber level, the wide pallet and to other tools. Roughnesses of the laid mix samovyravnivatsya and the surface quickly becomes smooth. Solution of a liquid consistence for thin layers (2-5 mm) spreads easily and samovyravnivatsya on all surface area. After drying, a floor needs to be grounded Aileron Soil solution
5. Features. Material is very plastic. It is easily leveled and smoothed. After a skhvatyvaniye the strong and plain surface is formed. According to the operational characteristics is frost-resistant, heatresistant, steady against attrition. A bulk floor "Aileron" does not contain the impurity making harmful effects on a human body.
6. Operation. At observance of all rules of care of the filled-in floor (avoidance of hit of direct sunshine, drafts, sharp difference of temperatures), at maintenance of optimum temperature moisture conditions (t = 10-25 °C, humidity of 60%), it is possible to operate a floor in 24 hours (a possibility of pedestrian circulation). It is desirable to make laying of a ceramic tile and other easy coverings not earlier than 7-14 days, depending on conditions of drying and thickness of a layer of a bulk floor. It is recommended to install heavy plates and coverings, mechanisms and the production equipment through 14 and more than a day depending on layer thickness.
7. Precautionary measures. To protect from children. At hit in eyes to wash out a large amount of water.
8. Packing and storage. It is delivered in kraft-bags weighing 25 kg ± 200 gr. A warranty period of storage of company packing in dry rooms - 6 months from the date of production. If technological conditions are violated, the producer is not responsible for result of the performed works.
|