(View map)
- Country of manufactureUkraine
Production of rectangular boot covers is divided into the following technology operations:
1. Production of preparation (package)
2. Podgib and soldering of elastic band or privarivaniye of ties.
Production of preparation (package)
For preparation production we recommend to use installation for welding of films of SHOV-500. Expendables - PE Film semi-sleeve, width of roll is equal to height boot covers (N). Welding time - 0,5-3 seconds (depending on film thickness). Productivity - to 10 000 preparations in change. (Human factor. The operator comes to required productivity in 3-4 days.) In case of purchase of ready packages of preparations in this car there is no need.
Privarivaniye of ties
Privarivaniye of ties is carried out during production boot covers on installation with curvilinear seams. In case of welding of ties there is no need to vvarivat elastic band. Welding of elastic band requires separate unit of equipment.
Podgib and soldering of elastic band
Special installation with bilateral heating is applied to podgib and soldering of elastic band. The operator's productivity on one installation - to 2 000 in change. Installation is executed on the basis of floor installations of the SEAM series.